Portugal / Alvalade Copper-Zinc VMS Project

Location Iberian Pyrite Belt
Ownership Optioned to Minas de Aguas Teñidas, S.A.  (MATSA)
Size 115 km2
Deposit Type VMS
Exploration Stage Exploration
Status Drill program underway
Presentation The Alvalade Opportunity
The Sesmarias Discovery

Avrupa acquired the Alvalade Project in 2010 and initially optioned it out in 2012, but has been the operator of the project since acquisition. During that first earn-in period (2012-15), an initial hole, SES002, was drilled into the Sesmarias target and intersected 10.85 meters of 1.81% copper, 2.57% lead and 4.38% zinc. Drilling encountered numerous faults, but subsequent holes hit mineralization, on and off, over an 800-meter strike length, including SES010 which intersected 58 meters of 0.32% copper, 0.61% lead, 1.95% zinc, 0.45 g/t gold, 25 g/t silver. There is still at least another 1,000 to 1,500 meters of known mineralization along strike to the north, encountered in historic drilling.

The new, upgraded Alvalade license covers approximately 115 square kilometres of highly prospective target area in a prime portion of the Iberian Pyrite Belt in Portugal.  The Sesmarias massive sulfide discovery lies just 7 kilometres south of the historic Lousal Mine and 9 kilometres south of our Monte da Bela Vista stockwork zone, all of which are covered by the Alvalade license.  Previous work at Sesmarias by Avrupa, itself, and by Avrupa with support from former JV partners, indicates that massive sulfide mineralization extends for at least 600 metres, may be as wide as 300 metres, and averages 25 metres in thickness.  Our work around Sesmarias also indicates that there is, at least, a further 2,000 metres of potentially mineralized target zone beyond the 600 metres of known massive sulfide mineralization.

Several technical sources estimate that the Lousal Mine originally contained upwards of 50 million metric tonnes of iron-, copper-, and zinc-bearing massive sulfide mineralization.  However, old mining records indicate that only 15-20 million metric tonnes of mineralized material were actually extracted during historic operations beginning in 1900 and continuing through 1988.  An independent consultant’s report commissioned by Avrupa in late 2017 suggests that Monte da Bela Vista-Lousal-Sesmarias could easily become a 50- to 100-million metric tonne copper-zinc, massive sulfide district.

In addition, the under-explored, historic Caveira Mine area is located just 9 kilometres north of Monte da Bela Vista, and between the two are several Avrupa scout drill holes that intersected sulfide mineralization.  Furthermore, Avrupa has drilled mineralized scout holes in several target areas along a 25-kilometer line from Sesmarias to the south end of the Alvalade license.

The Project is currently optioned out to Minas de Aguas Teñidas, S.A.  (MATSA) under the following terms:

In order to acquire a 51% interest in PorMining Lda.– “The Experimental Exploitation Phase”:

  • MATSA must provide to Avrupa 400,000 Euros (approximately C$ 580,000) payment upon signing of the Definitive Agreement.
  • MATSA must provide the required work commitment guarantee of 240,000 Euros (approximately C$ 348,000) upon issuance of the new Alvalade Experimental Exploitation License (EEL) to the new JV company (Newco), to be set up to hold the license. This amount is refundable to MATSA pending completion of the license work commitment and approval by the Portuguese Mining Bureau (DGEG).
  • MATSA must provide 2 million Euros (approximately C$ 1,740,000) for work on the Project during the first year after signing of the Definitive Agreement.
  • MATSA must provide, at its sole discretion, an additional 2 million euros for work over the second and third years of the joint venture.
  • Avrupa will be the Operator in this phase of work and will be paid 100,000 Euros (approximately C$145,000) annually as an operator’s fee.

In order to acquire a further 34% interest in PorMining Lda., for a total of 85% — “The Feasibility Study Phase”, MATSA must, at its option:

  • Provide a “bankable feasibility study” on one prospect within the Alvalade license. MATSA is responsible for 100% of the costs to produce the feasibility study, including preparation of a NI 43-101 compliant resource estimate;
  • Fund all necessary success-based payments to Avrupa’s previous joint venture partner, Antofagasta Minerals, S.A., as required by the Debt Cancellation Agreement between Avrupa and Antofagasta (see news release of June 19, 2017).

Project Commitment and Construction Phase:

  • In conjunction with the completion of the feasibility study, MATSA would be responsible to ensure that the application for a Mining License at Alvalade is completed, as required by Portuguese Mining Law.
  • During the Construction Phase, Avrupa will have the choice to participate as a 15% shareholder by providing its pro rata share of the necessary funding, or elect to transfer its 15% interest in PorMining Lda.to MATSA in exchange for staged payments of 10 million euros (approximately C$ 14.5 million), as follows:
  1. 3,000,000 Euros upon a construction decision being made, and the permits received from the DGEG;
  2. 3,000,000 Euros upon commencement of commercial production; and
  3. 4,000,000 Euros upon the first anniversary of commercial production.
  • The remainder of necessary success-based payments to Antofagasta would be borne by the Project, in accordance with the respective holdings in PorMining Lda..
  • Completion of the earn-in and joint venture arrangement remains subject to a number of conditions, including finalization of the Definitive Agreement itself, issuance of the Alvalade Experimental Exploitation License by the DGEG, and receipt of any required board and/or regulatory approvals. All legal due diligence has already been completed by MATSA.

A summary of some of the previously announced results from Alvalade is presented below:

  • SES002 – 10.85 meters @ 1.81% Cu; 75.27 ppm Ag; 2.57% Pb; 4.38% Zn; 0.13% Sn
  • SES006 – 1.5 meters @ 1.66% Cu; 54 ppm Ag; 2.30% Pb; 3.66% Zn; 0.091% Sn  — mineralization cut off by faulting
  • SES008 – 5.0 meters @ 0.64% Cu; 36.8 ppm Ag; 0.94% Pb; 1.54% Zn –   mineralization cut off by faulting
  • SES009 – 2.3 meters of massive pyrite (not analyzed)
  • SES010 – 57.85 meters @ 0.45 g/t Au; 25.1 g/t Ag; 0.32% Cu; 0.61% Pb; 1.95% Zn

The Project was optioned out a second time in Q3 2015.  During this earn-in period (2015-17), Avrupa drilled four additional holes into the Sesmarias target area that confirmed and extended one massive sulphide lens in the area to a length of 300+ meters with a 20-40 meter thickness. The lens is open to the northwest and down dip to the northeast.  The assays from those four holes are reported below.

Drill hole ID From
(m)
To
(m)
Intercept
(m)
Cu (%) Pb (%) Zn (%) Au (g/t) Ag (g/t)
SES019 263.50 315.20 51.70 0.44 0.75 2.71 0.40 17.35
including 264.15 299.05 34.90 0.40 0.99 3.46 0.38 20.67
and including 280.45 290.95 10.50 0.36 1.71 5.18 0.37 21.71
SES020 277.85 287.55 9.70 0.25 0.57 0.99 0.47 24.70
297.70 319.95 22.25 0.55 0.59 0.66 0.53 20.54
325.00 334.10 9.10 0.32 0.14 0.52 0.68 11.31
337.85 356.65 18.80 0.33 0.14 0.64 0.26 6.40
SES021 262.85 277.65 14.80 0.36 0.29 0.40 0.43 9.82
SES022 323.90 376.00 52.10 0.43 0.49 0.98 0.62 17.31

Table 1.  2015-16 drill intercepts from the SES010 lens.

In 2015, Avrupa conducted downhole geophysics, utilizing the “mise-a-la-masse” (MALM) method, and combined with historic ground magnetics data, suggested that the sulfide lens may continue another 300 meters or more to the northwest from SES022.

To date, 54 holes have been drilled around the license by Avrupa for a total of 21,121 meters.  More than 10 of the holes intercepted massive sulfides with various grades of copper, lead and zinc.

There are at least four other separate targets in the immediate Sesmarias area, a significant target in the Pombal area located about 15 km southeast of Sesmarias, and several targets at the Monte da Bela Vista stockwork discovery located about 10 km north of Sesmarias, all on the Neves Corvo mineral trend.  Numerous general targets exist on the Aljustrel mineral trend, on the São Domingos mineral trend, and in several other areas along the Neves Corvo mineral trend.  All three mineral trends cut the Alvalade license, giving a total of 85 km of prospective Pyrite Belt potential on the license.

In 2019, Avrupa completed a drill program consisting of 6 holes totaling 2,498 metres.  SES026 extended the “10” Lens by 300 metres to the north from previous drilling.

Plan view of the “10” Lens, “2” Lens, and “8-9” Lens/Horizon (red) and East Bounding Fault zone (transparent blue). The recently drilled holes are highlighted with a transparent box.

 

SES026 From (m)

To

(m)

Intercept (m) Au (g/t) Ag (ppm) Cu (%) Pb (%) Zn (%)
Total lens 385.70 414.65 28.95 0.77 15.7 0.48 0.52 1.31
Base metal zone 385.70 392.70 7.00 0.52 19.0 0.66 0.57 1.44
Gold zone 392.70 401.70 9.00 1.09 13.7 0.40 .50 1.31

 

Assays for SES003 were returned in 2019 and the results are comparable to those from SES002, as shown in the table below.

SULFIDE TYPE

FROM

TO

TOTAL

Cu %

Ag ppm

Pb %

Zn %

Sn %

Co %

Massive/semi-massive

132.05

145.70

13.65

1.92

38.8

1.03

1.91

0.03

0.103

 

FROM

TO

TOTAL

Cu ppm

Ag ppm

Pb ppm

Zn ppm

Co ppm

Weak/moderate stockwork

145.70

152.50

6.80

4133

7.42

3908

11645

296